Building Walker's Landing

Construction Updates

Dated photos and video from the Walker's Landing site, Warner Robins, Georgia — updated every month as the build progresses.

This page is our running record of construction progress at Walker's Landing. Each month we add new site photos and video so you can follow the build from streets and utilities through to completed townhomes.

SEP2026

September 2026

Latest

Streets and underground utilities are complete. Electrical conduit is being installed next, ahead of the concrete foundation slabs, which are followed by vertical construction of the townhomes.

Complete

Streets Formed

Curb & gutter poured, stone road base laid.

Complete

Utilities In

Water, sewer & stormwater drainage installed.

Then

Concrete Slabs

Foundation slabs poured on the graded pads.

Then

Vertical Construction

Framing and build-out of the townhomes.

🎥 September 1 — Cement Slabs Update

📷 Site Photos — Late August / September 2026

Walker's Landing community entrance on Hickory Street with Wind & Water Homes project sign and newly poured curbing
Community entrance off Hickory Street — Wind & Water Homes project signage up and curb and gutter poured along the new road.
Internal street at Walker's Landing with curb and gutter poured on both sides and roadway subgrade prepared
Internal streets taking shape — curb and gutter poured both sides and the roadway prepared for paving.
Compacted stone road base through a Walker's Landing cul-de-sac with formed concrete landscape islands
Compacted stone road base through the cul-de-sac, with concrete curbing and landscape islands formed.
Completed cul-de-sac bulb at Walker's Landing with curbing and aggregate base
A cul-de-sac bulb complete with curbing and aggregate base while crews finish the surrounding lots.
Wide view of Walker's Landing showing stone-based streets, formed islands and graded building pads with equipment on site
Wide view: stone-based streets, formed islands and individual building pads staked and graded — ready for foundations.
Graded lots at Walker's Landing with utility works, a power pole and construction equipment
Lots graded and utilities trenched in, with power, water and sewer services being brought through the site.
Concrete sidewalks poured along the street frontage at Walker's Landing with perimeter landscaping
Concrete sidewalks poured along the street frontage, with perimeter landscaping and site signage in place.
Stormwater detention pond at Walker's Landing with concrete flared-end outfall structure installed
Stormwater detention pond with concrete outfall structure installed — site drainage infrastructure complete.
Detention pond and graded embankment at Walker's Landing bordered by established homes and mature trees
Graded pond embankments backing onto an established neighbourhood of homes and mature trees — a true infill location.

More updates coming next month — check back soon.

Photographs and video are taken on site and shown for progress-update purposes only. Construction sequencing and timelines are subject to weather, permitting and contractor scheduling. This page is updated monthly as new material becomes available.

🌐 Language: